Division of Emergency and Remedial Response
Voluntary Action Program Site Cleanup Summary
HARRISON WEST
Address:
525 West First Avenue
Columbus, Ohio 43215
Property also known as:
A.C. Humko
Capital City Products
Columbus Forge and Iron
Acreage:
11.185
County of site:
Franklin
Volunteer name and location:
Royal Tallow Holdings, Ltd. and
Harrison Park Development, Ltd
1289 Grandview Avenue
Columbus, Ohio 43212
City of Columbus
Department of Development
109 North Front Street
Columbus, Ohio 43215
Certified professional:
Atul Pandey (CP224)
Certified laboratories:
EA Group (CL0015)
Blackhand Laboratory (CL0064)
Merit Laboratories, Inc. (CL002)
Environmental Science Corporation (CL0069)
NFA number:
06NFA231
Date no further action letter submitted:
March 9, 2006
Date covenant not to sue issued:
September 13, 2006
Remedial Activities:
Removal by modified soil vapor extraction of methane and hydrogen sulfide gases.
Removal by extraction of approximately 87,229 tons of PAH and TPH-contaminated soil from the former acid plant and the triangular and truck garage underground storage tank areas.
Removal of approximately 800 gallons of free phase petroleum product from the former acid plant area excavation.
Removal by excavation of approximately 2,316 tons of PAH and metals-contaminated soil from the former railroad spur area.
Removal of approximately 1, 632 gallons of free phrase petroleum product and ground water from recovery wells.
Removal of asbestos from buildings prior to their demolition.
Institutional control(s):
Not applicable
Engineering control(s):
Not applicable
Operation and maintenance agreement:
No
Urban setting determination approved:
Not applicable
Attachment 1:
September 13, 2006 Covenant Not to Sue
Attachment 2:
March 13, 2008 Audit Report
Summary date:
May 2008
For further information contact:
Ray Moreno
Ohio EPA, DERR, CDO
P.O. Box 1049
Columbus, OH 43216-1049
614-723-3833